432 Park Avenue rises 1,396 feet above Midtown Manhattan on a footprint 93.5 feet square. Its height is about 15 times its width, giving the tower a slender profile that responds to wind. The design includes concrete frames, a central core, open floors and two tuned mass dampers near the top.

Movement is part of the engineering plan. Comfort and daily reliability are separate concerns, and a board lawsuit describes creaking, banging, clicking, vibration and difficulty sleeping during bad weather. A 2021 report, citing a management email, said a resident was trapped in an elevator for 1 hour and 25 minutes on October 31, 2019.

A home that moves

The tower's structural engineer, Silvian Marcus, describes an outer concrete moment frame working with a central concrete shear-wall core. The two systems act together to resist wind and support the floors. The exposed white columns and beams around the windows are part of that structure.

Early wind-tunnel tests found strong vortex shedding. As wind passes a square tower, alternating swirls of low pressure can pull it from side to side. If that rhythm approaches the building's natural frequency, the motion can increase. The design team carried out about 5 force-balance tests, held workshops and then used aeroelastic models that flexed like the full-sized tower.

The engineers set a comfort target of less than about 0.1 metres per second squared of sideways acceleration during a gale expected about once a year. That is approximately 1% of gravitational acceleration. A person lying still in a quiet bedroom may notice sounds or small visual cues before consciously sensing the movement itself.

Open floors and elevator delays

Five two-story open floors interrupt the tower's solid wall surface. They allow wind to pass through and reduce the wind load, especially from vortex shedding. These levels also contain mechanical equipment, while five two-story outriggers connect the central core to the perimeter frame at roughly corresponding locations. The openings change the airflow. The outriggers transfer structural forces between the core and the outside frame.

Wind can affect the elevator system because cables hanging inside a shaft can swing as the tower moves. The complaint alleges that 432 Park's elevators were programmed to slow during high winds and sometimes shut down completely. A February 5, 2021 report, citing a management email and earlier New York Times reporting, said that a resident became trapped on the evening of October 31, 2019, for 1 hour and 25 minutes during a reported high-wind condition. The management email has never been published, so who was inside and on which floor is unknown.

The tower has 4 residential elevators, according to the board's complaint. A separate Schindler project record says the company supplied 11 elevators and 2 escalators for the project as a whole. In November 2018, a leak on the 60th floor was followed 4 days later by a leak on the 74th floor. The board alleged that water from the higher leak entered the elevator shafts and left 2 of the 4 residential cars out of service for weeks.

People inside the machine

A 2015 marketing report listed a 24-hour doorman, a private restaurant, in-suite dining, room service, a garage and valet parking. Current listings also advertise round-the-clock doorman and concierge service and in-suite dining. The front door is staffed through the night, on windy and calm nights alike.

The same 2015 report described 25 studios on floors 28 and 29 for residential support staff. Whether household employees live in those units today has not been established. The tower's lower floors experience less wind-driven motion than the upper levels.

The reports of discomfort came through a condominium board lawsuit. The board identified Richard Ressler, CIM's chairman and a unit owner, as having described the noise and vibration as "intolerable." The complaint also says that sleep became difficult during periods of moderately bad weather. It lists creaking, banging and clicking, along with a trash chute that owners compared to a bomb. The trash chute is a separate waste system, so its noise cannot be assigned to the tower's wind response.

In September 2021, the sponsor said the building had performed well, described some repair items as common in new construction and said owners had blocked access for repairs. The condominium board filed a second amended complaint on May 9, 2023, containing its allegations about noise, sleep difficulty, elevators and water damage.

Two weights near the roof

Near the top are 2 opposed-pendulum tuned mass dampers. Steel weights hang from cables and connect sideways to viscous dampers. When the tower moves, the weights lag behind its motion. The viscous devices absorb some of the resulting energy, reducing the movement felt by people inside.

Installation records describe each damper as a large steel box filled with mass plate. About 200 pieces were assembled for each one, with more than 8,000 bolts used across the pair. Crane work took 8 weeks, followed by 4 weeks of adjustment. The weights had to be tuned to move in relation to the tower.

Engineering sources give different masses. One describes 2 units of 660 tons, another gives 650 tonnes each and an installer gives 600 tons each. The exact mass and the floors the dampers sit on remain unresolved.

Step by step

  1. November 2017Schindler said it had supplied 11 elevators and 2 escalators for the project.
  2. November 22, 2018A reported water failure occurred on the 60th floor.
  3. November 26, 2018A second reported water failure on the 74th floor was followed by 2 residential elevators being unavailable for weeks.
  4. October 31, 2019A management email reportedly described an elevator stoppage during a high-wind condition that lasted 1 hour and 25 minutes.
  5. September 24, 2021A report described the board's complaints and the sponsor's response that the building had performed well and that some repair items were common in new construction.
  6. May 9, 2023The condominium board filed a second amended complaint containing its allegations about noise, sleep difficulty, elevators and water damage.

What the video leaves out

Fox Business, citing Department of Buildings records, reported a separate facade history. A 2022 notification classified facade conditions as unsafe, followed by repairs and a February 2023 SWARMP report, meaning Safe With a Repair and Maintenance Program. A reported April 15, 2025 filing also carried a SWARMP designation. The agency was reported on October 24, 2025 as knowing of no current unsafe facade condition requiring pedestrian protection.

On June 2, 2026, an appellate decision denied Macklowe indemnification under the condominium documents and dismissed related counterclaims.

The documentary How People Sleep in a 1,400-Foot Tower That Sways in the Wind
Watch on YouTube

Sources

  1. People Seeking Help Above Midtown Manhattan
  2. People Seeking Help Above Midtown Manhattan
  3. One Hour Twenty Five Minutes
  4. CIM Chairman Tower Development Source
  5. CIM Group Tower Development Information
  6. 432 Park Avenue Tower Height
  7. 432 Park Avenue Height Proportions
  8. Tall Buildings Move In Wind
  9. 432 Park Avenue Waste System Complaint
  10. Developer Response To Building Complaints
  11. Unpublished Management Email About Elevators
  12. High Wind Elevator Safety Shutdowns
  13. 432 Park Avenue Elevator Delays
  14. Silvian Marcus Structural Engineer Description
  15. Additional 432 Park Avenue Source
  16. Thin Tower Wind Testing Challenge
  17. Early Wind Tunnel Vortex Shedding
  18. Wind Motion Acceleration Comfort Target
  19. Building Movement Relative To Gravity
  20. Milli G Building Motion Measurement
  21. Building Motion Warning Signs Explained
  22. Building Motion Warning Signs Explained
  23. 432 Park Avenue Wind Openings
  24. 432 Park Avenue Building Amenities
  25. 432 Park Avenue Resident Amenities
  26. 432 Park Avenue Resident Amenities
  27. 432 Park Avenue Concierge Services
  28. 432 Park Avenue Concierge Services
  29. Resident Restaurant Kitchen Operations Information
  30. 432 Park Avenue Water System Failure
  31. 432 Park Avenue Plumbing Complaint Details
  32. 432 Park Avenue Structural Concrete Grid
  33. New York Building Facade Inspection Requirements
  34. New York Building Facade Inspection Requirements
  35. 432 Park Avenue Tuned Mass Dampers
  36. 432 Park Avenue Tuned Mass Dampers
  37. Taipei 101 Tuned Mass Damper
  38. Taipei 101 Tuned Mass Damper
  39. Taipei 101 Damper Movement Reduction
  40. Taipei 101 Damper Movement Reduction
  41. Taipei 101 Damper Soudelor Swing
  42. Taipei 101 Damper Maximum Swing
  43. Taipei 101 Damper Tourist Attraction
  44. Taipei 101 Damper Tourist Attraction
  45. 432 Park Avenue Sway Control System
  46. Building Sway Noises During Storms
  47. Elevator Slowdown Experiences By City
  48. We Got Stuck Elevator
  49. Stuck In OTIS Elevator
  50. 432 Park Avenue Drone
  51. 432 Park Exterior Drone Tour
  52. 432 Park Avenue Construction Timelapse
  53. Torsional Aeroelastic Wind Testing
  54. 432 Park Avenue Mass Damper
  55. 432 Park Avenue Construction Timelapse
  56. Taipei 101 Skyline Drone Flight
  57. Taipei 101 Typhoon Damper Movement

Sources come from the research behind the video. Found an error? Write to [email protected].